Lots of Work Done but Nothing to Invoice Yet: Managing Work in Progress and Cash in Thailand

A guide for contractors, agencies and service companies that have done the work but cannot bill yet: how to measure and report unbilled work in progress, age it, split it by cause, set billing milestones and contract terms that shorten the wait, and run a weekly review.

Suwanvara Law Firm— Business Law TeamNovember 21, 202614 min read
Lots of Work Done but Nothing to Invoice Yet: Managing Work in Progress and Cash in Thailand

The core answer

Unbilled work in progress is money the company has already spent but has no documented right to collect yet. If it is not measured and reported regularly, the number grows quietly until there is not enough cash for payroll and suppliers, even while projects run and sales look good.

Managing it has three parts. First, measure it correctly by separating "done", "accepted by the customer" and "billable under the contract". Second, age it and split it by cause, then give each pile to a named person. Third, fix it at the source, with milestones and contract terms that tie payment to checkable evidence, and a rule on who inside the company may approve extra work.

This guide is about management and drafting in advance, not the dispute where a customer refuses to sign acceptance. For that, see Delivered but the customer won't sign acceptance, so you can't invoice, which covers the hire-of-work rules, section 602, the acceptance person and a follow-up timeline.

Who should read which part

Your situationRead sections
Before deciding: about to take on a job or quote, terms can still change5, 6, 7 and 10
In progress: work is running, several projects at once1 to 4, 8 and 9
When the numbers are off plan: unbilled work growing fast, cash tight3, 4, 9 and 11

1. What is unbilled work in progress, and why does it hit cash?

Work in progress, or WIP, is work done in whole or in part for which no invoice has been issued. The costs in this stage are real: team wages, subcontractor fees, materials, and media or independent-contractor costs an agency has paid out in advance. The revenue has not arrived.

Keep it distinct from receivables.

ItemArises whenFixed through
Unbilled workWork done or costs paid, but billing conditions not yet metMilestones, acceptance, extra work, approvals
Invoiced receivablesInvoice issued, waiting for the customer to payCredit terms and collection. See Unpaid invoices from business customers

Contractors and agencies are especially exposed because costs always come before revenue. The more the contract leaves the final instalment until after acceptance, the longer the gap.

2. How to measure it so the numbers do not mislead

Use three separate figures.

FigureMeaningSource
A. Value of work doneWork actually completed at the cut-off dateProgress reports, timesheets, site records
B. Accepted by the customerThe part the customer has accepted or confirmed in writingAcceptance forms, approval emails
C. Billable under the contractThe part that has reached its milestone or billing cycleContract, work order, milestone schedule

The gap A minus B shows money stuck at acceptance. The gap B minus C shows money stuck in the milestone structure: the work is accepted but the contract does not yet let you bill.

Points to watch

  • Percent-complete figures based on the team's feeling tend to run high near the end of a job. Tie them to evidence, such as deliverables sent, hours against budget, or items the customer approved.
  • Costs already paid are not a reason to invoice unless the contract says costs are rechargeable.
  • How revenue and work in progress are recognised in the financial statements is for the company's accountant or auditor. This guide gives no accounting or tax guidance.

3. Age the unbilled work

Count age from the date each item became "billable if conditions are met", or from the delivery date, and sort into piles.

AgeMeaningWhat to do
Up to 30 daysNormal for work just deliveredCheck there is a named acceptance person and a review deadline
31 to 60 daysStarting to look wrongProject manager contacts the customer and records the outcome
61 to 90 daysEscalateManagement speaks to the customer's decision-maker and checks the contract terms
Over 90 daysHigh riskDecide whether to continue or stop work, and ask the accountant about valuation

The 30, 60 and 90 day bands are common examples only. Adjust them to the company's credit terms and type of work. Construction may use longer bands than a monthly agency retainer.

The report should fit on one page: customer, project, unbilled amount, age, cause, owner, and the date it is expected to become billable.

4. Split by cause and assign someone to fix it

CauseWho must actFix
Customer has not accepted or is not respondingProject manager, then managementFollow the acceptance timeline in the acceptance guide, improve terms on the next job
Next milestone conditions not yet metProject managerCheck what is missing, or ask for finer milestones
Extra work not approvedProject manager and approverSeek written approval, or stop that work
Supporting documents incomplete, such as delivery note or customer purchase orderAccounting and project teamList the documents that must accompany delivery
Customer changed requirements mid-jobProject managerRecord the change, assess effect on time and price, get it in writing
Customer purchase order or project code expired or not yet openedSales or project teamCheck before starting, and do not work without a reference number

Once the causes are split, most turn out not to need a lawyer. They need internal discipline and clear contract terms.

The hire-of-work rules bear directly on when you can bill. Section 602 of the Civil and Commercial Code provides that the contract price falls due when the client accepts the work, and that where delivery in parts was agreed together with payment in parts, each part falls due on acceptance of that part. In practice, if the contract is not clear on acceptance and milestones, billing comes later than the contractor expects.

Milestone approaches that help manage work in progress

  • Tie milestones to checkable output, such as first draft delivered or zone 1 installed, not "50 percent of the work".
  • On long jobs, use smaller and more frequent milestones so the unbilled amount at any time stays within what cash can carry.
  • Name the acceptance person, the channel and the review deadline in the contract, and state the result if the customer stays silent beyond it. Draft carefully. See the acceptance guide on "deemed acceptance" clauses.
  • Where the customer reviews in rounds, separate minor corrections from the billing test for that milestone, to the extent you can agree it.

6. Extra work and changes: costs that arise before approval

Extra work is the biggest source of work in progress that never becomes an invoice, because the team does what the customer asks but there is no extra quote or approval.

Working rules

  • Set a rule that out-of-scope work needs a change order or an approval email from the customer's authorised person before it starts, stating the price or how it is priced and the effect on the deadline.
  • In urgent cases where work must begin first, send a message confirming scope and estimated price and ask for a reply. Keep it in the project file.
  • In the WIP report, show extra work on separate lines labelled "approved" or "not yet approved". Do not mix it with work under the main contract.
  • Unapproved extra work above the project manager's limit goes on the agenda of the weekly meeting.

How to keep evidence of extra work ordered by chat is in Extra work ordered on LINE.

7. Internal approval authority: who starts work, who signs acceptance, who stops work

Many companies lose money because people on site decide beyond their authority without realising. Write a short authority table everyone can see.

DecisionApprover (example structure)
Starting before the contract or work order is signedManagement only, stating conditions and a cost ceiling
Accepting extra work within a set limitProject manager, with the customer's approval on file
Accepting extra work above the limit, or changing the deadlineDirector or authorised director
Signing the delivery note or acceptance record for the companyA person the company names
Stopping work when the customer is behind on instalments or has not approvedManagement, after checking the contract terms
Discounting or waiving extra workAuthorised director, in writing

The limits in the table must be set for your own business. The table is an example structure, not a recommended figure. A fuller approval-authority table is in Setting up contract review when there is no legal department.

Always check the contract terms and evidence before stopping work. Stopping without a contractual right may itself become a breach by your side.

8. Contract terms that shorten the wait

These must be agreed with the customer before work starts and written into the contract or work order.

TermHow it helpsCaution
Advance or first instalment on signingCovers start-up costsState what happens to it on cancellation, and whether it counts toward the price
Milestones tied to checkable evidenceMakes the billing point clearWrite criteria that can actually be checked
Monthly billing for hours or actual costNo waiting for project endNeeds timesheets and an agreed rate
Cut-off date and acceptance deadlineLimits the waiting periodName the acceptance person and the notice channel
"Deemed acceptance" when the customer is silentReduces delay caused by silenceKeep it reasonable, as a court may look at the facts and fairness
Payment due on invoice, not tied to money the customer receives from othersYour money does not wait on someone else's paymentIf the main contract ties it, assess the risk before accepting
Right to suspend work when payment is overdueStops further costs piling upNotice must be given in writing as the contract requires

Large customers often send their own standard contract. Check the payment and acceptance terms before signing. See A big customer sent us its contract.

9. The weekly unbilled work review

Keep it short, no more than an hour, using the one-page report from section 3.

Agenda itemKey question
1. Total and movementDid unbilled work rise or fall since last week, and by how much?
2. Items past their age limitWhich items are over 60 days, who is contacting whom, what was the result?
3. Extra work awaiting approvalHas any extra work been done without approval evidence? Seek approval or stop?
4. Milestones due in the next 2 weeksAre billing conditions met, what documents need preparing?
5. Cash in and outIf this milestone is late, what can cash cover?
6. Contract terms to fix on the next jobHow should recurring problems be written into new contracts?

Record decisions as a short list with an owner and a date. Start the next meeting from that list.

10. Checklist before quoting and accepting a job

  • Milestones are tied to checkable output, not loose percentages
  • There is an advance or first instalment, or you have assessed that cash can carry the early costs
  • The acceptance person, review deadline and result of silence are stated
  • Scope and the method for requesting changes or extra work are stated, with the customer's authorised approver
  • The documents needed with each invoice, such as purchase order and delivery note, are stated
  • You have checked whether payment is tied to money the customer receives from someone else
  • Internal approval authority and limits for extra work are set
  • A weekly WIP review is in the project calendar

11. When the numbers are off plan

  • Build the ageing table from section 3 this week, with unapproved extra work shown separately
  • Collect delivery evidence, acceptance forms and approval emails for each item
  • Management speaks to the customer's decision-maker on items over 60 days
  • Forecast cash for about the next 13 weeks. See Profitable but short of cash
  • Ask the accountant about recording work in progress, value added tax and assessing amounts that may not be collected
  • If the customer rejects the work or disputes it, follow the acceptance guide and the trade-debt collection guide
  • Decide whether to take new work from this customer or wait for payment first

Hypothetical example: a campaign agency

This is a hypothetical example, not a real case. All figures are illustrative and are not market benchmarks.

An agency takes a campaign worth 1,000,000 baht in three milestones. Milestone one is 30 percent on signing, milestone two is 40 percent when the customer accepts the creative work, and milestone three is 30 percent when the campaign ends and the report is delivered.

At one weekly WIP review the figures are:

ItemBaht
Value of work done (75 percent of the contract)750,000
Invoiced and paid (milestone one)300,000
Total unbilled work450,000
Costs already paid out520,000
Net cash tied up (costs paid less money received)220,000

The 450,000 baht splits by cause as follows.

  • 200,000 baht is waiting for the customer to accept the creative work for milestone two. It was delivered 40 days ago and no acceptance person was named.
  • 150,000 baht is extra work done on a chat request, with no written approval.
  • 100,000 baht is milestone three work that has not yet reached its billing condition.

In the meeting, management calls the customer's decision-maker to name an acceptance person and a review date. The project manager emails a summary of the extra work with a price and asks for a reply, and no new extra items are taken until the earlier ones are approved. Accounting takes the figures to the accountant on how to record them, and the team revises the template contract, splitting milestone two into two parts by checkable output and adding an acceptance deadline.

The example shows that the 450,000 baht is not one problem but three piles with different owners and fixes.

Common misunderstandings

MisunderstandingCorrection
The work is finished, so I can invoice straight awayThe right to payment depends on the contract and acceptance, under section 602 and the milestone terms agreed
Costs I have paid equal what the customer must pay meCheck how the contract prices and recharges. Costs you have advanced are not automatically a right to payment
Extra work done on a customer's chat request is definitely approvedIt may be provable if the evidence is clear, but it is still a risk. Confirm price and scope in writing
WIP numbers are only the accounting team's businessProject managers and management fix most of the causes. Accounting reports and analyses
A "deemed acceptance" clause always lets me invoiceIt works within what was agreed and what is reasonable. The real result depends on the facts and the delivery evidence
I can stop work the moment the customer is late payingCheck your contractual right and follow the notice steps first, or you may be the party in breach

Further reading

Work in progress does not turn into cash by itself. Measure it as three figures, age it, give every cause an owner, and set milestones and approval authority before the work starts.

We help review and draft contracts, work orders, milestone schedules, acceptance terms and internal approval-authority tables, as well as letters requesting approval of extra work and notices to customers. We are not accountants or auditors, so we do not advise on bookkeeping or tax, and we cannot promise that a customer will approve or pay. Fees depend on the stage of the matter and the work required. Send us the documents first, and we will give you the scope of work and fees in writing before we start. Call +66 92 254 2045 or send us the details. See also contracts and documents and accounting and tax.


This guide is published by Suwanvara Law Firm — a Khon Kaen law firm established in 1986. General information only, not legal advice on a specific matter.

Frequently asked questions

What is unbilled work in progress, and how is it different from receivables?+

It is work the company has done in whole or in part, with costs already incurred, but for which no invoice has been issued. Receivables are amounts already invoiced and waiting for the customer to pay. Look at the two separately because the causes and fixes differ. The first is fixed through acceptance, milestones and extra-work approval. The second is fixed through payment follow-up. How each is recorded in the accounts is for your accountant to decide.

What should work in progress be measured against?+

Use three separate figures: the value of work done, the value the customer has approved or accepted, and the value the contract actually lets you invoice under its milestone terms. The gaps between them show where the money is stuck. A single figure based on the team's feeling tends to run high and does not match what can be billed.

Should extra work done before approval be counted as unbilled work?+

Show it on its own line, marked as not yet approved in writing, and keep it apart from work the customer has accepted. Your right to payment depends on the contract and on evidence that the customer ordered or accepted the work. Management then sees the real risk and can decide whether to seek approval after the fact or stop that work. For evidence, see the guide on extra work ordered through LINE.

Which contract terms shorten the wait before billing?+

Commonly used terms are milestones tied to checkable evidence rather than loose percentages, an advance or first instalment, a monthly billing cut-off for time-based or actual-cost work, a named acceptance person with a time limit, and a stated result when the customer stays silent. All of it must be agreed with the customer beforehand and written into the contract or work order, not announced by one side after the work is finished.

How often should unbilled work be reviewed, and who attends?+

For a company running several projects at once, review weekly, for no more than an hour. The minimum attendees are the project manager, finance or accounting, and someone with approval authority. The agenda is items past their age limit, extra work awaiting approval, and actions before the next meeting, each with a named owner and a date.