After the BOI Certificate: Deadlines, Reporting, Project Amendments and Why Privileges Get Revoked

A BOI promotion certificate comes with conditions that run for years: machinery import and start-up deadlines, e-Monitoring reports, permission before changing the project, and limits on duty-exempt machinery. This guide sets out what to do, what happens when privileges are revoked, and what to check before selling, transferring, moving or retiring machinery that used a privilege.

Suwanvara Law Firm— Corporate & Investment TeamOctober 9, 202610 min read
After the BOI Certificate: Deadlines, Reporting, Project Amendments and Why Privileges Get Revoked

Short answer

Conditions after a BOI promotion certificate differ from company to company, so read them from the company's own certificate and project conditions. The common ones are deadlines, reports, amending the project before any change, and limits on duty-exempt machinery.

If you plan to sell, transfer, move or retire machinery that used a privilege, do not start by looking for a buyer. First find out which privilege the machine used, what its status is and what obligations are still running, then ask BOI before you act.

Your situationSections to read
Certificate just issuedDeadlines after issue, e-Monitoring reports, using the tax and duty privileges
Project is runningChanges that need prior permission, duty-exempt machinery, checklist
A change is coming (selling machines, moving the plant, changing shareholders)Duty-exempt machinery, hypothetical example, when privileges are revoked

The certificate is a contract with conditions

A promotion certificate grants privileges on the conditions written in it: the product or service, capacity, location, investment amount and any condition specific to the activity. As long as the company uses the privileges, those conditions bind it. The usual problem is not deliberate breach but a business that changed while nobody amended the project to match reality.

Post-approval work falls into five areas: deadlines, reporting, using the privileges, changing the project, and keeping the conditions in place for as long as the privileges last.

Deadlines after the certificate is issued

ItemDeadline
Import machineryWithin 30 months of the certificate date
File to start full operationWithin 36 months of the certificate date
Software, platform or digital content development (item 8.1.1)Full operation within 12 months, not extendable
ISO 9000 or ISO 14000 (projects of THB 10 million or more)Within 2 years of full operation

General deadlines can be extended under the office's criteria, but the request must be filed before the deadline expires, and some activities cannot be extended. Starting full operation means showing that the company has met the conditions in the certificate, including investment, machinery, capacity and any specific conditions. It is not just starting to produce or sell.

Reporting through e-Monitoring

Promoted companies must report through BOI's e-Monitoring system. Projects not yet in full operation report progress in February and July, and projects in operation report results in July. Reports cover compliance with conditions such as ISO standards and, where the project needs one, an environmental impact assessment report.

An overdue report affects more than the system status. It can affect other work, such as renewing foreign employees' work permits through the BOI channel, which looks at the project's status. See the work permit and visa guide for the BOI channel.

Using the tax and duty privileges

Machinery duty is used through the eMT system. The company files its main machinery list for the office to review, which takes about 60 working days, and then requests release of each shipment through the system, which can be approved within 3 hours. Planning machinery imports and second-hand machinery are covered in the guide to importing machinery for a new factory.

Duty on raw materials for export is used through RMTS Online. A list of raw materials and the production formula must be approved first, and the account is then drawn down by the quantity actually exported.

Corporate income tax. The exemption period starts from the date income is first earned from the promoted activity, not the certificate date (section 31). The company must keep the income and expenses of the promoted activity separate from other income, because income outside the certificate is not exempt. Losses in the exemption period can be carried forward for 5 years after the period ends, and dividends from the tax-exempt activity are not included in taxable income (section 34).

Changes that need prior permission

These need an application to amend the project, not a report afterwards.

  • Change of registered capital or shareholding ratios. Where the foreign shareholding rises, the office may ask for evidence that funds were brought in from abroad.
  • Changing or adding products or services.
  • Changing capacity.
  • Moving the project location.
  • Changing any other condition written in the certificate.

Once the documents are complete, the office considers this type of amendment within about 5 working days. The time actually lost is usually in finding out too late, not in BOI's process.

A foreign company in List 2 or List 3 of the Foreign Business Act receives a section 12 certificate only for the promoted activity. If it expands into other business outside the certificate, the licence under that law must be considered separately. See the guide to 100% foreign ownership in Thailand.

Duty-exempt machinery

Section 40 of the Investment Promotion Act requires the Board to set a period of between 5 and 15 years during which the company may not use duty-exempt machinery outside the promoted activity, may not let others use it, and may not move the place of business without permission. Section 41 allows the Board to permit a sale, mortgage, lease or move case by case.

This affects several business decisions, such as letting an affiliate share a production line, pledging machinery as security for a loan, or moving the plant. Ask for permission before acting.

What to check before selling, transferring, moving or retiring machinery

Check against the company's own certificate and conditions. There is no single rule for every business.

CheckWhat to look at
Privilege historyIs the machine on the machinery list BOI approved? When was it imported and released? Was the duty exemption used in full or in part?
Machine statusIs it still used in the project and at the location in the certificate? Where is it installed? Is it mortgaged, leased or used by an affiliate? Is the breakdown or retirement real?
Obligations still runningHas the section 40 restricted period set by the Board for the company ended? Other conditions in the certificate? Loan or hire-purchase contracts with the machine as security?
DocumentsCertificate and amendment letters, machinery list, import documents and release records, asset register, draft sale or lease contract
Effect on capacityIf retiring the machine changes the capacity or process in the certificate, a project amendment may be needed as well

Working rules

  • Ask BOI for permission or guidance before signing and before delivery, not after the sale.
  • Do not read the restricted period from an article. Look at the conditions and period BOI set for your company.
  • Even if you believe the restricted period has ended, have BOI confirm in writing that no steps or conditions remain open.
  • For the duty and tax result for each machine, ask customs and have an accountant check it. We do not give figures or rates we have not verified.
  • Information as of 21 November 2026. The rules may change, so check the latest announcements on the BOI announcements page.

Foreign employees

The right to bring in skilled workers and experts under sections 25 and 26 attaches to the approved position, not to the person. BOI office announcement No. Por. 8/2568 added criteria for approving foreign skilled workers and experts for certificates issued from 1 January 2026, including a Thai-employee ratio test for large manufacturing activities. Companies certified in this period should check their staffing plan against the new criteria before applying for position approval.

When privileges are revoked

Section 54. If the company does not comply with the conditions, the Board may revoke the privileges in whole or in part. If the Board considers the breach unintentional, it may first have a warning letter with a deadline to cure sent.

Section 55. On full revocation, the company is treated as never having received the privileges and must pay the duty on the exempted machinery and raw materials according to their condition, value and rate on the import date. On partial revocation, only the revoked part is payable, and the company must contact Customs within 1 month.

Section 56. If the company is dissolved, merged or transferred, the certificate remains effective for no more than 3 months, and a transferee that wants the privileges must obtain its own promotion, so raise it with BOI before that period ends. A sale or group restructuring involving a promoted company therefore needs the BOI steps in the closing timetable from the start.

Checklist after the certificate

  1. Make a schedule of the machinery import, full operation and ISO deadlines
  2. Name who is responsible for the February and July e-Monitoring reports
  3. File the machinery and raw material lists before the goods arrive
  4. Keep the income and expenses of the promoted activity in separate accounts
  5. Get permission before changing shareholders, capital, products, capacity or location
  6. Get permission before selling, mortgaging, leasing or moving duty-exempt machinery
  7. Check the foreign staffing plan against the 2568 criteria
  8. Put the BOI steps in any sale or group restructuring plan
  9. Make a register of machines that used a privilege, with status, location, encumbrances and the restricted period under the company's conditions
  10. Put your question to BOI in writing before selling, transferring, moving or retiring machinery, and keep the reply

Hypothetical example

This is not a real case and the numbers are only illustrative. Company A makes parts on 6 plastic injection machines and used the duty exemption when importing them. A buyer later offers to buy machines 5 and 6, which are no longer in use.

The company found that machine 5 was on the machinery list and still within the restricted period under the company's conditions, while machine 6 was mortgaged to a bank. It did not sign. It built the table above and wrote to BOI with the documents. Only if BOI permits will it settle terms with the buyer and the bank. The result for each machine can differ depending on the facts and the certificate's conditions.

Common misunderstandings

BeliefReality
We bought the machine, so we can sell it whenever we likeIf the machine was duty-exempt, check sections 40 and 41 and the company's conditions first
The machine is out of use, so there is no need to tell BOIRetiring it may affect the capacity or process in the certificate, so ask first
Another company sold, so we can tooEach company's certificate and conditions differ
The restricted period is over, so nothing else is neededHave BOI confirm that no conditions or steps remain open
An affiliate can share the machine because the owner is the sameSection 40 bars others from using it in the set period, and an affiliate is a separate legal person

Further reading

Machinery that used a BOI privilege is not an ordinary asset. Check the certificate and the machine's history first, then ask BOI before you act, every time.

We help review the promotion certificate, project conditions and machinery documents, and draft the letter to BOI and the sale or transfer contract. We are not accountants or tax auditors, we do not act in place of the BOI office, and we cannot guarantee the outcome of its decision. Fees depend on the stage of the matter and the work needed. Send us the documents first, and we will confirm the scope and fee in writing before we start. Call +66 92 254 2045 or send us the details. See also our BOI investment legal advisory service and contracts and documents service.


This guide is published by Suwanvara Law Firm — a Khon Kaen law firm established in 1986. General information only, not legal advice on a specific matter.

Frequently asked questions

What deadlines apply after the promotion certificate is issued?+

Under the 2025 BOI guide, machinery must be imported within 30 months and the application to start full operation filed within 36 months of the certificate date. Some activities have shorter, non-extendable deadlines; software development, for example, must reach full operation within 12 months. Progress must be reported through e-Monitoring in the meantime.

Do I have to tell BOI about a change of shareholders or a capital increase?+

You must apply to amend the project before or together with the change, not report it afterwards. Changes to registered capital, shareholding ratios, products, location or capacity all need approval. Where the foreign shareholding rises, the office may ask for evidence that funds were brought in from abroad.

Can duty-exempt machinery be sold or moved?+

During the period set by the Board, between 5 and 15 years, section 40 of the Investment Promotion Act bars using duty-exempt machinery outside the promoted activity or letting others use it, and bars moving the place of business without permission. Section 41 lets the Board permit a sale, mortgage, lease or move case by case.

What happens if BOI conditions are breached?+

Section 54 lets the Board revoke privileges in whole or in part. If the Board considers the breach unintentional, it may first have a warning letter with a deadline to cure sent. On full revocation, section 55 treats the company as never having received the privileges and duty is payable on the condition, value and rate on the import date.

Does the promotion certificate survive a sale of the business or a merger?+

It does not transfer by itself. Section 56 lets the certificate of a company that is dissolved, merged or transferred remain effective for no more than 3 months, and a transferee that wants the privileges must obtain its own promotion, so raise it with BOI before that period ends. A deal involving a promoted company therefore needs the BOI steps written into the contract and the closing timetable.

What should I check before selling, transferring or retiring machinery that used a BOI privilege?+

Start with the company's own certificate and conditions, then go through the machine's privilege history, its current status, obligations still running (such as the section 40 restricted period and finance contracts) and the related documents. Ask the BOI office before the transaction, not after. Customs and tax consequences depend on the facts of each machine, so have customs and an accountant check them as well.