The core answer
When the condominium juristic person announces a special levy for major repairs, do not pay straight away and do not refuse straight away. Check four things in this order.
- Who has authority to approve it. The manager, the committee or the owners' general meeting. The answer is in the registered regulations, not in a notice by the lift.
- Whether the approving meeting was valid. Notice, an agenda item that names the levy, quorum, a voting record and signed minutes.
- How your unit's amount was worked out. Is it by the ratio set in the regulations, and where does the total come from?
- Whether project documents back it up. Engineer's report, quotations from several contractors, scope of work, schedule, reserve fund balance and financial statements.
If all four are in order and the reasons are sound, paying is usually the right course. If one is missing, request documents in writing, keep proof that you asked, and object within the payment period. Refusing without a ground that can be defended has consequences similar to unpaid common fees.
This guide describes the Condominium Act in plain words. It gives no section numbers or voting percentages, because those must be checked against your building's regulations and the current text of the Act. Information as of 21 November 2026.
Who this guide is for
| Your situation | Read |
|---|---|
| No dispute yet, you have just been told of a meeting or a levy | Sections 1, 2, 3 and the document checklist |
| Problems have started: the levy looks unclear or the meeting looks irregular | Sections 4, 5, 6 |
| You have received a demand or a threat to restrict services, or a case has started | Sections 6, 7 and the hypothetical example |
Unpaid monthly common fees and how the juristic person collects them are covered in our guide on common-fee arrears. This page does not repeat that. It deals with a one-off special sum for major repairs, which needs a clear source of authority and a joint decision more than ordinary fees do.
1. How is a special levy different from monthly common fees?
Monthly common fees are what every unit pays regularly to run the building under the annual budget. A special levy is a lump sum requested because the normal budget and the reserve fund are not enough, for example to:
- repair or replace the lifts
- repair or replace the roof and rooftop
- repair the exterior walls or glass facade
- waterproof the roof, basement or pool
- replace the fire system, alarm system or water pumps
Three things justify a closer look than usual. The amount is often many times the monthly fee, the work can be procured in many ways, and real needs can sit next to unnecessary extras. At the same time, some repairs cannot wait, especially on safety. Checking documents is not obstruction. It separates what is necessary from what is not, and checks that the decision followed the right steps.
2. Who has authority to approve a special levy?
The Condominium Act makes the juristic person responsible for the common property, with a manager acting for it and the owners' meeting deciding important matters. Which matters the manager can handle alone, which need committee approval and which must go to the general meeting depends on each juristic person's regulations and the law in force.
| Decision-maker | What to look for in the regulations |
|---|---|
| Manager | Spending limit without approval and what must be reported |
| Committee | Matters that need committee approval, how it votes, the highest amount it may decide |
| Owners' meeting | Matters reserved for the general meeting, the type of meeting, and the vote required |
Ask for authority to be shown in documents, not for "this is how it has always been done". Request the latest registered regulations and, if they were amended, proof of the registered amendment. The quorum and voting thresholds that actually apply come from those two sources. Check the current text through the Department of Lands or the Council of State. This guide gives no figures.
3. Was the approving meeting valid?
A levy approved at a properly held meeting stands on firmer ground than one simply announced. If the meeting was defective, the resolution may be challenged. Check:
| Item | What to ask |
|---|---|
| Notice | Was it sent to every owner by the method and in the time the regulations require? Is there proof of sending? |
| Agenda | Does it name the special levy, or was it buried under "other matters"? |
| Attachments | Were the engineer's report, price comparison and the figure to be approved sent with the notice? |
| Quorum | Did the owners or ownership shares present meet the regulations' requirement? |
| Voting | Were votes counted as the regulations require, proxies handled correctly, and results recorded? |
| Minutes | Were they prepared and signed, and do the resolution and amount match what you were billed? |
Common problems in practice: an agenda so broad that owners could not tell a levy was coming, or a resolution that approves "doing the repair" but not the amount charged to each unit. If you find either, list it as a specific objection in your letter.
4. How is each unit's amount worked out?
As a rule, each owner bears the cost of common property in the ratio set by the law and the regulations, which usually follows the unit's registered share of ownership in the common property. A unit with a larger share pays more, and a smaller share pays less. It is not always split equally.
Check three points:
- Your unit's share. Compare your title for the unit or the condominium register with the table the juristic person used.
- The building-wide calculation. The sum of all units' amounts should equal the figure the meeting approved. If it does not, ask what the difference is.
- Works that serve only some owners. For example a lift in one block of a multi-building project. Check whether the regulations allow different shares.
If you bought the unit second-hand, also check whether the levy belongs to the period of the previous owner or to the time after transfer. That should be settled when you buy. See our guide to buying a resale condo from a private seller.
5. Which project documents should I ask for, and how?
| Document | What it lets you check |
|---|---|
| Condition report by an engineer or specialist | Whether the damage is real, how urgent it is, who signed and with what qualifications |
| Quotations from several contractors | Whether prices were compared, why this contractor was chosen, whether the contractor is connected to a committee member or the manager |
| Scope of work (bill of quantities) and drawings | Whether the work matches the problem in the report or goes beyond it |
| Schedule and timeline | How payments are staged, who accepts the work, whether there is a warranty or retention |
| Reserve or sinking fund balance | How much the juristic person holds and what is used before extra money is called |
| Latest financial statements | What past fees were spent on and whether a major-repair budget was set aside |
| Per-unit calculation table | Whether your amount matches your registered share |
| Meeting minutes and voting papers | Whether the resolution was valid (section 3) |
Sample wording of a request
Send the letter to the juristic person's manager, copy the chair of the committee, and keep proof of delivery. A short version:
I am the owner of unit ... I have been told to pay a special levy for ... in the amount of ... baht, due on ... Please send copies of the following within ... days: (1) the specialist's report; (2) all quotations and the reasons for the choice of contractor; (3) the scope of work and schedule; (4) the reserve fund balance and the latest financial statements; (5) the calculation of my unit's amount; (6) the notice, minutes and voting record of the meeting that approved this. While I wait for these documents I reserve all my rights to object to the amount.
Set a clear reply date. Do not write "I refuse to pay" before you have seen the documents. "I request documents and reserve my rights" is safer.
6. If something looks wrong, how can I object?
Go from lighter to heavier steps and use the cheaper channel first, unless a deadline is close.
- Raise it at the meeting. If the meeting has not happened yet, ask for questions about documents and the method of calculation to be placed on the agenda, or ask them at the meeting and have them recorded in the minutes.
- Request documents in writing as in section 5, because those documents decide whether your objection has weight.
- Send a written objection on specific points. State what you object to, for example a defective meeting, a wrong ratio, or no document showing the work is necessary. "I disagree" alone is not enough. Pay any part that is not in dispute, if the amount can be split, so you cannot be accused of defaulting on all of it.
- Complain to the competent authority. Condominiums are registered with the Department of Lands and its local land offices, so you can ask them whether your complaint is within their powers. That depends on the nature of the complaint.
- Court as a last resort. A court may examine the validity of a resolution or the right to charge where there is a dispute. It takes time and money, so have your documents ready before deciding.
Avoid actions that hurt your own position, such as posting accusations against committee members in an owners' chat group, or refusing to pay and ignoring the letters. Both can weaken an owner who had good grounds.
7. What happens if I refuse to pay without a valid ground?
If the resolution is valid, the amount is correct and the documents are in order, but the owner still does not pay, the following can happen:
- extra charges or penalties under the regulations
- restricted use of shared facilities such as the pool or gym, where the regulations allow it
- written demands, followed by a suit for the unpaid sum
- when you sell or transfer, the juristic person may withhold the certificate that no money is owed until you pay, which delays the sale
The tools and process are explained in our common-fee arrears guide. If a suit is brought over a special levy, the court will look at both the validity of the resolution and the amount demanded, so keep proof of your document requests and objections.
This is different from a water leak, where liability has to be traced case by case. If damage comes from one particular unit, see our guide on water leaks from the unit above.
8. Hypothetical example
Hypothetical example (not a real case; the figures are illustrative only). A fictional condominium has 100 units. The juristic person announces a special levy totalling 5,000,000 baht to replace the fire system on an engineer's report. The reserve fund holds 1,000,000 baht, so it asks for a further 4,000,000 baht.
Khun Mani owns a unit with 1 percent of the building's ownership share. The amount billed to her is 40,000 baht, which matches 1 in 100 of 4,000,000 baht.
She checks in order:
- Authority. The regulations say works above a set amount go to the general meeting, and this one qualifies.
- Meeting. She asks for the minutes. The agenda in the notice said only "building system improvements", with no amount to be charged and no engineer's report attached.
- Amount. A 1 percent share matches the register, and the building total is 4,000,000 baht.
- Documents. She asks and receives the engineer's report and three quotations, but not the financial statements or the reserve fund balance.
She accepts that the work is needed, so she does not refuse to pay. She sends a letter pointing out the defects in the agenda and attachments, asks for the financial statements, and asks that the resolution be put to another meeting with complete documents. In this example the juristic person might call a new meeting, or explain that its authority was valid. What matters is that one letter contained both proof that she asked for documents and specific grounds, which is what a court or an agency would look for if the matter went that far.
9. Checklist of documents and actions
- Get the latest registered regulations and proof of any amendment
- Check whether the regulations give the manager, committee or general meeting authority over this matter
- Keep the meeting notice with proof of the date received, and check the agenda
- Request the minutes, voting results and the list of attendees and proxies
- Request the engineer's or specialist's report and all quotations
- Request the scope of work, schedule and staged payment terms
- Request the reserve fund balance and the latest financial statements
- Check your unit's share against the register and check the building total
- Send a request for documents that reserves your rights before the due date, and keep proof of delivery
- Put the due date and the juristic person's reply date in your calendar
- Pay any undisputed part if the amount can be split, and object to the rest in writing
- Take legal advice if the juristic person refuses to show documents, threatens to sue or restricts services
Common misunderstandings
| Misunderstanding | Correction |
|---|---|
| A notice from the juristic person means I must pay immediately | First check whether the person issuing it has authority under the regulations and whether approval followed the right steps |
| Once the resolution is passed, I cannot ask anything | A valid resolution binds co-owners, but you can still request documents and check how your unit's amount was calculated |
| I disagree with the repair, so I do not have to pay | Disagreement is not an exemption. You need a specific ground, such as a defective resolution or a miscalculated amount |
| Quietly stopping payment is safer than objecting in writing | Silence can look like default without cause. Object in writing within the payment period |
| Every unit pays the same | The split usually follows the ratio in the regulations, which is tied to ownership share. Check your building's regulations |
| Urgent safety repairs need no documents or meeting | Urgent work may start first, but billing every owner still needs a basis and documents |
Further reading
- Unpaid common fees: a guide for condominium and village juristic persons
- Water leak from the unit above: who is liable
- Buying a resale condo from a private seller
- How long a civil case takes
Before paying a major-repair levy, check who approved it, whether the meeting was valid, how the amount was worked out and what project documents exist, then object in writing within the payment period rather than staying silent or paying without looking.
We advise on reviewing regulations, meeting resolutions and project documents, on drafting document requests and letters of objection, and on litigation where a juristic person and an owner dispute a special levy. We are not engineers or building inspectors, so we cannot judge whether a repair is technically necessary. We are not auditors, and we cannot promise the result of a dispute. Fees depend on the stage of the matter and the work required. Send us the documents first and we will give you the scope of work and fees in writing before we start. Call +66 92 254 2045 or send us the details. See also our land law services and real estate services.
This guide was prepared by Suwanvara Law Firm — a law firm in Khon Kaen, established in B.E. 2529. It is general information and not legal opinion for any particular case. The outcome of each matter depends on the title documents and the facts on the ground.