The core answer
When your house starts to crack after a neighbour drives piles, excavates or uses heavy machinery, first gather the evidence, then have a qualified independent engineer inspect the house and write a report. The cause of cracks must be assessed by an engineer, not concluded from photographs alone, because houses crack for many reasons and old and new cracks can look alike.
Strong evidence usually has four connected parts: the condition of the house before and after, a timeline of the neighbouring works, project documents such as the permit, plans and contractor's name, and the engineer's report. With those in hand you prepare a damage list, send a written notice and negotiate. Court is considered only if negotiation fails.
The point to watch most closely is limitation. Section 448 sets one year from the day the injured person knows of the wrongful act and who must pay, or ten years from the day of the act. See section 8.
Which stage are you at?
| Stage | Sections to read first |
|---|---|
| No dispute yet (the neighbour has just announced or started building) | Sections 2, 3 and 4. Photograph and measure the house first and ask for an engineer's survey before heavy work begins |
| Problems have started (cracks, sticking doors, broken tiles during or after the work) | Sections 1, 5, 6 and 7. Engineer's report, damage list and written notice |
| Letter received or case filed (the other side denies, a lawyer has replied, or you have been sued) | Sections 7, 8 and 9. Who may be liable, limitation, and the order before court |
1. What cracks can and cannot tell you
Cracks come in many types. Fine lines along the joint between wall and column may come from shrinkage or temperature. Diagonal cracks, cracks that keep widening, sloping floors and warped doors or windows may relate to foundation movement. You can see that something is wrong, but the effect of nearby works on the structure must be assessed from engineering data such as the foundation type, soil, distance, work method and movement history.
- Photos show where a crack is, how large, and when the photo was taken.
- Photos do not show whether the crack came from the neighbouring works or another cause.
- Photos taken after the event also cannot answer the neighbour's claim that "your house was already cracked".
This is why both sides need an engineer's opinion, and why before-and-after evidence matters: it gives the opinion data to rest on.
2. What before-and-after evidence should you collect?
The aim is to make it possible to trace who photographed what, where, when and with which device.
| Item | How to collect it |
|---|---|
| Dated photos and video | Cover inside and outside: walls, floors, ceilings, columns, fence, paths. Take wide and close shots with a ruler or scale next to the crack. Keep the original files; do not edit or compress them |
| Crack measurements | Measure width and length with a measuring tool, mark the ends of the crack in pencil with the date, repeat weekly or monthly and record in a table. If the engineer advises a crack gauge, follow the advice |
| Older photos from before the work | Search your phone, cloud, social media, party photos, repair photos, sale or rental listing photos |
| Other abnormal signs | Doors or windows not closing, tilting floors, new standing water, leaking pipes, pressure changes. Record the date you first noticed each |
| Witness statements | Write down names, addresses, relationship and what they saw: household members, tenants, a housekeeper, repairers who worked on the house, other neighbours |
Do not repair before photographing and having the engineer look. If an emergency repair is needed for safety, photograph first, keep quotations and receipts, and say in writing why you repaired.
3. How to build a timeline of the works
A timeline shows which phase of work the cracks followed. Add to it every time something happens, starting from the day you learn that work will begin next door.
| Date | Event | Evidence |
|---|---|---|
| When you first learned of the work | Notice, site sign or what the neighbour said | Photo of the sign, chat messages |
| Start of excavation or piling | Type of work, machines used, working hours | Video, photos of machines |
| Day you felt vibration | Strength, duration, who was present | Short note made that day |
| Day you saw a new crack | Location and size | Dated photo, measurement |
| Day you notified the neighbour or contractor | How, and who received it | Letter, postal receipt, message |
| Day you notified the authority | Reference number, name of recipient | Copy of the letter, receipt |
Add one more line, "the date I learned who carried out the work", because the one-year period under section 448 runs from the day the injured person knows of the wrongful act and who must pay.
4. What documents can you ask the neighbour and contractor for?
These help the engineer assess more accurately. You may not obtain all of them; ask the neighbour first and ask the local authority for what you are entitled to under its procedures.
- Building or extension permit and the plans submitted (where one is required)
- Names of the project owner, contractor and site supervisor with contact details
- Work methods used, such as driven or bored piles, excavation depth, soil support
- The actual working period
- The contractor's construction insurance or third-party liability insurance, if any
- Any photos or report the other side made of your house before the work began
If you ask and they refuse, keep your request and its date. Do not enter their land to photograph; take photos from your own land or a public place.
5. The independent engineer and the report
Choose a qualified engineer with no interest in the neighbour or contractor. You can ask whether they hold a professional engineering licence in a relevant field and whether they have written building damage assessments before. A useful report contains at least the following.
- Who engaged the engineer, the inspection date, who inspected, qualifications, and the information received
- The condition of the house: structure type, foundation, age, past repairs
- A plan and location of every crack with size, photos and measurements
- Facts about the neighbouring works: type, distance, dates
- Analysis of whether each group of cracks is consistent with the neighbouring works, whether there are other causes, and how confident the conclusion is
- Recommendations: urgent repair, monitoring, shoring or temporary evacuation, and permanent repair
- Limits of the inspection, for example visual only or with test probing
If the neighbouring works are still going on, have the engineer re-inspect at intervals, since cracks that keep growing are important data. You are the client, but do not ask the engineer to write the conclusion you want. A neutral report is more credible, and if it says the main cause is not the neighbouring works you will know before sending a demand.
6. How to prepare the damage list
Use a table, one item per line, with evidence for each. Figures must come from real documents, not rough guesses.
| Category | Example items | Evidence |
|---|---|---|
| Repair costs | Walls, floors, roof, electrics, plumbing | At least two contractors' quotations, receipts, photos before and after repair |
| Inspection and report | Engineer's fee, survey | Receipts, engagement letter |
| Temporary accommodation | Rent, moving and storage while the house is unusable | Lease, receipts, the engineer's advice to move out |
| Loss of use | A room that cannot be used, lost business or rental income | Lease, income records, photos |
| Damaged belongings | Furniture, appliances, fittings | Photos, purchase receipts, repair quotations |
| Other necessary costs | Travel to follow up, postage for notices | Receipts |
Take care: you can claim only damage connected to the neighbouring works as the engineer assesses it. If some cracks were already there or come from other causes, separate them so the claim stays credible and is not rejected as a whole. Upgrades that make the house better than before, such as newer materials, may be disputed as not being damage.
7. Who may be liable, and which laws are relevant
Who may be involved
- The project owner or the neighbour extending, if they ordered the work or controlled the method
- The contractor, if the work was done negligently, for example no soil support, or a piling method unsuited to the distance
- The designer or site supervisor, in some cases, depending on their duties under the contract
Who is actually liable depends on the facts: who employed the workers, who decided the method, who knew or should have known of the risk. Name both the owner and the contractor in your notice rather than choosing one at the start.
Sections 420 and 1337
- Section 420: a person who intentionally or negligently unlawfully causes damage to the life, body, health, liberty, property or any right of another commits a wrongful act and must pay compensation. In general the injured person must show an act, damage, and that the damage came from that act, which is why an engineer's report is needed.
- Section 1337: where a person exercising his right causes an owner of immovable property damage or nuisance beyond what could be expected as normal and reasonable, taking the nature and location of the property into account, the owner has the right to act to bring that damage or nuisance to an end, without losing the right to compensation.
In plain terms, building on your own land is allowed, but if the effect on the neighbouring house goes beyond what is normal for the area, the affected owner may demand that the damage stop and claim compensation. What counts as "beyond" is a question of fact for the court case by case. Cracks alone do not mean you will win.
A note on digging near a boundary: this guide does not go into excavation right at the boundary line. If your case also involves a boundary or an encroaching fence, read Land disputes, boundaries and adverse possession alongside it.
8. Limitation: when must you act?
Section 448 says a claim for damages arising from a wrongful act is time-barred after one year from the day the injured person knows of the wrongful act and who must pay compensation, or after ten years from the day of the wrongful act. If the claim arises from an act that is a criminal offence with a longer criminal limitation period, that longer period applies.
In practice:
- One year is short. If you negotiate informally for a long time with nothing in writing, time can pass without your noticing.
- The date you "knew of the wrongful act and who must pay" is a fact the other side may dispute, so record when and how you learned it.
- Notices and negotiation do not stop the clock automatically. Ask a lawyer what is needed to protect your rights well before the deadline.
- If further damage appears later (cracks widen), the counting may need case-specific analysis.
9. First steps: written notice, local authority and negotiation
A. A written notice to the neighbour and contractor
Send it by registered post with return receipt, or another way that proves delivery. Keep it short and factual: the date you began to notice problems, the cracks found (attach photos and the table), a request to stop or adjust methods that may affect your house until an engineer has inspected, a request for project documents, an invitation for their engineer to inspect jointly, a request that they notify their insurer if any, and a reply deadline. Do not threaten or accuse them of intentional destruction.
B. Ask the local authority to inspect
The local authority (municipality, subdistrict administrative organisation or Bangkok Metropolitan Administration, depending on location) oversees permits and building control in its area. File a written request asking an officer to check whether the neighbouring work has a permit and follows what was approved, and keep a copy with the date of receipt. The result may be useful information, but the authority does not decide compensation between you and the neighbour and does not replace your engineer's report.
C. Negotiate and settle in writing
A good settlement states what the other side will do (repair, pay, or both), who does the repair and to what standard, the deadline, how the work will be accepted, who is responsible if the same works cause further damage, and how the settlement affects any remaining claims. Do not sign a release or accept money under wording such as "no further claims" before the engineer has assessed the full damage, because some cracks appear later.
D. Court as a last resort
If negotiation fails, or limitation is near, then consider suing. The documents from sections 2 to 6 are the base. The court may call the engineer as a witness or appoint an expert. Cost, time and uncertainty are why most people try to negotiate first where they can.
10. Checklist before sending the notice
- Photographed and filmed the whole house; kept the original files
- Measured and marked each crack and started a dated table
- Collected older pre-work photos and a list of witnesses
- Built a timeline of the construction
- Asked the neighbour for the permit, plans and contractor's name
- Engaged an independent engineer and received a written report
- Prepared the damage list with quotations and receipts
- Noted the date you learned who did the work and counted the limitation period
- Sent the notice with proof of delivery
- Filed with the local authority and kept a copy
- Not yet signed any release or accepted money under "no further claims" wording
Hypothetical example: piling next to a two-storey house
This is not a real case and the figures are illustrative only.
Mr Somsak lives in a 15-year-old two-storey house. He sees a sign that a three-storey building will be built next door. He photographs and films the whole house, measures two fine existing cracks and records them in a table. Three weeks after the contractor starts piling, he feels vibration every day, finds a new diagonal crack in a ground-floor wall, and the back door begins not to close properly.
He does not argue on site. He photographs and measures the new crack, notes the date, and asks the neighbour for a copy of the permit, which gives him the contractor's name. He engages an independent engineer. The report says the new diagonal crack in the ground-floor wall is consistent with the piling period, that the two original fine cracks are unrelated to the neighbouring works, and recommends monthly monitoring.
Mr Somsak prepares a damage list. Say two repair quotations come to between 80,000 and 100,000 baht (hypothetical figures), not including the engineer's fee. He sends a registered letter to the project owner and contractor with the report and the list, asks for a meeting, and files a request with the local authority to check the permit. After two rounds of negotiation, the contractor agrees to repair to the standard set by the engineer and to monitoring for six more months. Mr Somsak has the agreement written to say that if further damage arises from the same works, his rights are not ended.
Observation: he did well because he had before-and-after evidence and a report separating old cracks from new. Had he sent only post-event photos and said "you cracked my house with your piling", the other side could have refused easily.
Common misunderstandings
| Misunderstanding | Correction |
|---|---|
| "Photos of the cracks are enough to sue; they show the cause" | Photos show that cracks exist, not why. A qualified engineer must assess the cause from the site and documents |
| "My house cracked after they built, so they are at fault" | Matching timing is important, but other causes and whether the work was intentional or negligent still have to be considered |
| "They have a permit, so they cannot be liable" | A permit does not always mean the work was done without negligence. The effect on neighbouring houses still depends on the facts and the engineer's report |
| "The local authority will inspect and make them pay" | The authority looks at permits and building control. It does not decide compensation between neighbours |
| "I can negotiate for as long as it takes" | The one-year period under section 448 runs from knowing of the wrongful act and who must pay. Negotiation does not stop it automatically |
| "I must sue before I can claim" | Normally you start with a notice and negotiation. Court is the last resort |
| "Once I accept repair money I can still claim for new cracks" | A document saying no further claims may be used against you, so read it carefully and have an engineer assess first |
Limits of this guide. This is general guidance for homes affected by neighbouring construction on private land. It does not cover public projects, government works, disasters, detailed insurance claims, a case where you are the one commissioning the building, or a condominium where the damage is in common areas. Different facts can change the answer.
Further reading
- Land disputes, boundaries and adverse possession: if the neighbouring work crosses the boundary or there is a land dispute
- Building a factory or commercial building: contract terms every project owner needs before work starts: if you are the one commissioning the building
- Condo water leak from the unit above: who is liable and what evidence to keep: damage coming from someone else's property in a condominium
- Lawyer fees and scope of work
Takeaway: gather before-and-after evidence and a timeline, have an independent engineer assess the cause in writing, prepare a documented damage list, then give written notice and negotiate in writing, keeping the one-year period under section 448 in view throughout.
Our land dispute team advises on preparing evidence, coordinating with an engineer or other expert, drafting notices, negotiating and litigating, but we are not engineers, we do not diagnose structural causes, and we cannot promise the outcome of a case. Fees depend on the stage of the case and the work required. Send us your documents first, and we will give you the scope of work and the fees in writing before we start. Call +66 92 254 2045 or send us the details — we keep it confidential.
This guide was prepared by Suwanvara Law Firm — a law firm in Khon Kaen, established in B.E. 2529. It is general information and not legal opinion for any particular case. The outcome of each matter depends on the title documents and the facts on the ground.