Orders Are Up but Delivery Is Slower: How to Find the Bottleneck Before Buying Machines or Hiring

How to find the bottleneck in your production or service line before spending on machines or staff: map the process, measure throughput, queue time, work in progress, set-up time, rework and downtime, compare the options, and review what sales promised customers and what the machine purchase contract says.

Suwanvara Law Firm— Business Law TeamNovember 21, 202614 min read
Orders Are Up but Delivery Is Slower: How to Find the Bottleneck Before Buying Machines or Hiring

The core answer

When orders are up but delivery is slower, do not buy a machine or hire first. Find which step in the line limits everything else, the bottleneck. The whole line can deliver only as much as its slowest step. Adding capacity at any other step barely speeds up deliveries; the work just piles up in front of the bottleneck.

Finding it is not difficult. Map the process as it is actually done, from order intake to delivery, then measure six things per step: real output per hour, queue time, work in progress in front of the step, set-up time, rework or scrap, and downtime. Once you know the bottleneck, compare the options: change the method or the schedule, overtime or an extra shift, outsourcing, buying a machine, or hiring.

The legal link. Capacity figures are a management matter, but their consequences land in contracts. If sales promised delivery dates or penalties beyond real capacity, the company may be liable to customers. If the machine purchase contract does not fix delivery, acceptance testing and warranty clearly, the investment carries avoidable risk.

This guide is about finding a bottleneck in the process flow. If your question is whether to add headcount, see Before hiring more staff: workload, capacity and cost. If you decide to buy machinery from abroad, see Importing machinery for a new factory.

Who should read which part

Your situationSections to read
Before deciding: nothing bought or hired yetSections 1 to 5 to find the bottleneck and compare options; sections 8 and 9 for the contracts to review before committing money
In progress: machine bought or people hiredSections 2 and 3 to check whether the new machine or people actually relieve the bottleneck; section 9 for acceptance test and warranty terms
Numbers are off plan: deliveries later than promised to customersSection 7 (hypothetical example), section 8 (what sales promised) and section 10 (checklist)

1. How do you map the process so the bottleneck shows?

Draw it as it is really done, not as the manual or an old flow chart says. Have the people who do the work help, because steps added informally, such as waiting for a sign-off or moving work between departments, are often where work gets stuck.

  • Draw every step as a box in order, from order intake to delivery and payment collection.
  • Under each box, note who or which machine does it and how many units of capacity there are.
  • Mark where work waits, for example for materials, customer information, inspection or transport.
  • Mark where work loops back for rework, since that is capacity spent with no extra output.
  • Follow one real job from start to finish and record when it enters and leaves each step.

For a service business the boxes might be intake, request for more information, document check, preparation, supervisor review, customer approval, delivery. Waiting for customer information and waiting for approval often take longer than the work itself.

2. What should you measure at each step?

Measure all six before drawing conclusions. Use at least one or two weeks of normal work and record what happens rather than estimating.

MeasureMeaningHow to read it
Throughput per stepUnits the step really completes per hour or dayThe lowest figure is the main suspect
Queue timeHow long work sits in front of the step before anyone startsVery long waits in front of a step mean it cannot keep up
Work in progress (WIP)Number of jobs parked between stepsA large pile in front of one step often points to the bottleneck; small piles after it are normal
Set-up (changeover) timeTime spent adjusting a machine, changing a mould, colour or job, during which nothing is producedIf jobs change often, this eats a large part of bottleneck capacity
Rework and scrapShare of work that is redone or thrown awayRework at or after the bottleneck makes usable capacity lower than the paper figure
DowntimeTime the step cannot work: breakdown, waiting for repair, breaks, missing materialDowntime at the bottleneck is lost output for the whole line

Measure usable capacity after set-up, downtime and rework. Nameplate capacity is usually higher than what is achieved, which is why people buy new machines while the old ones still hide capacity.

3. How do you tell the bottleneck from a step that is just busy?

The busiest-looking step is not always the bottleneck. The bottleneck is the step whose usable capacity is lowest compared with the volume that must pass through it. Check in this order.

  1. Find the step with the largest pile in front of it and the longest waiting time.
  2. Compare its usable capacity with the daily volume you must deliver. If capacity is lower, that step is the bottleneck.
  3. Check that the steps after it are idle waiting for work. That confirms the bottleneck limits the whole line.
  4. Test it: help that step temporarily, for example by moving a person or taking rework away from it, and see whether deliveries really go up.

Bottlenecks move. Once you fix one step, another becomes the limit, so measure again after every change. A bottleneck is also not always a machine. It can be a single specialist, a single approver or a wait for outside information.

4. Why does buying a machine or hiring away from the bottleneck not help?

A line is like a pipe that is narrow at one point. Pouring more in at the start does not make more come out at the end. If you add a machine or a person upstream, work reaches the bottleneck faster, WIP and waiting time grow, and lateness can get worse. If you add downstream, that step simply waits for work.

The financial result is higher capital cost and payroll with the same deliveries. Before approving a budget, ask the proposer whether the machine or person is at the bottleneck and how much the usable capacity of that step will rise. Return-on-investment calculations should be reviewed by an accountant or auditor.

5. What are the options for raising capacity at the bottleneck?

Go from the cheapest and most reversible to the most binding. The table is a framework, not a conclusion; real results depend on each business.

OptionUse whenWatch out for
Change method and scheduleHigh set-up time, a lot of rework, work waiting for information or approvalMeasure before and after; may need training and a different order intake process
Re-sequence jobs, for example batch similar jobsFrequent changeoversMay affect some customers' delivery dates; check the promises in your contracts
Overtime or an extra shift at the bottleneckA temporary surge in demandMust follow labour protection law (section 6); not suitable as a permanent fix
Outsource some stepsThe bottleneck is a specific step, or demand is uncertainNeeds a contract on quality, delivery dates, confidentiality and liability to the end customer
Buy or lease more machinesThe bottleneck is machine capacity and method changes are not enoughHigh investment and lead time; check the purchase contract (section 9)
Hire more peopleThe bottleneck is really people capacity at that stepLook at cost and workload across the whole system; see the staffing guide referred to above

The first two rows are usually the fastest and cheapest, so try them before committing money to machines or permanent staff.

6. Overtime and extra shifts: what to watch under labour law

Overtime or an extra shift at the bottleneck is a common supplement, but labour protection law sets a framework. In broad terms only:

  • Overtime generally needs the employee's consent, as the law requires, not simply an order.
  • Overtime and work on rest days carry additional pay as the law and agreements require.
  • There are limits on working hours, with further restrictions for certain types of work and certain groups of employees.
  • Shift work must allow the rest periods the law requires.

Hour limits and rates can change by notification, so check with the Ministry of Labour or have a lawyer check before using them. If you need overtime every week just to deliver on time, that signals the bottleneck is not fixed. See labour law information from the Ministry of Labour.

7. Hypothetical example: a packaging plant with rising orders and late deliveries

This is not a real case. All figures are illustrative only, to show the method.

A hypothetical plant prints and forms boxes. Orders have grown so that it must ship 450 units a day but ships about 360, and the backlog grows every week. The manager is thinking of buying another assembly machine, but first measures the line (8-hour shift):

StepOutput per hourActual working time per dayReal output per dayPile in front
Cutting1208 hours960Small
Printing606 hours (two changeovers a day, 1 hour each)360Largest
Assembly908 hours720Small
Inspection and packing1008 hours800Small

Printing is the bottleneck. Its real output of 360 units a day equals actual shipments. Assembly has plenty of spare capacity, so a new assembly machine would not help.

Options tried in order:

  • Cut each changeover from 1 hour to half an hour by preparing moulds and ink while the press is still running. Working time becomes 7 hours and output 420 units a day.
  • Group orders with the same colour so printing runs continuously, reducing changeovers to one a day of half an hour. Working time becomes 7.5 hours and output 450 units a day, matching the required volume.
  • If demand rises further, consider overtime at printing, outsourcing some print jobs, or a second press.

The first two cost little and can be done quickly. Re-sequencing jobs affects each customer's delivery date, so the manager checks the contracts and order confirmations before changing the order. Other plants may see different results, depending on their line and measured data.

8. What did sales promise customers, and what should you review?

Rising orders usually come with sales promises: delivery dates, response times, priority and penalties. Before changing the line or buying a machine, collect every promise and compare it with real capacity.

  • Delivery date: fixed date, within a number of days of the order, or subject to capacity, and when the clock starts.
  • Penalty or late-delivery damages: a daily rate, whether there is a cap, and whether it replaces or adds to actual damages.
  • Priority: whether large or long-term customers rank first, and what delaying one customer does to the others.
  • Minimum volumes and ordering terms: how much the company promised it can accept in a period.
  • Exceptions: force majeure, late customer information or materials, and rights to extend time.

The general rule in the Civil and Commercial Code is that if a debtor does not perform as the obligation truly requires, the creditor may claim damages for the resulting loss (section 215). If the contract fixes a penalty for non-performance, the creditor may claim the penalty instead of performance (section 380), and a court may reduce a penalty that is disproportionately high (section 383). Whether and how much the company would owe depends on the contract wording, the cause of delay and the facts.

If a promise exceeds real capacity, do not stay silent and hope to catch up. Check whether a written change of date or extension can be negotiated, and require sales to check capacity with production before promising again. For force majeure and cost increases, see Force majeure vs cost increases in contracts.

9. Before buying a machine, what should the purchase contract say?

If measurement shows the bottleneck really is machine capacity and method changes are not enough, a machine is a long commitment. The supplier contract should be clear on the following.

TopicWhat to specify
Delivery and installation datesDelivery date, installation date, who handles transport and installation, and the consequence of late delivery such as damages or a right to terminate
Acceptance testThe criteria for passing, such as output per hour and scrap rate, who tests, where, and what happens if it fails
PaymentHow it is split into instalments and whether the final instalment depends on passing the test
WarrantyDuration, what is covered and excluded, and who pays labour and freight for repairs
Spare parts and after-sales serviceAvailability and for how long, and response time when the machine breaks down
Training and documentsWhether the supplier trains staff and supplies manuals
Governing law and dispute resolutionWorth fixing clearly if you buy from abroad

Sale-of-goods law provides that where the thing sold has a defect that reduces its value or its fitness for its normal or contractual use, the seller is liable as the law provides (section 472). In practice, write the acceptance criteria and the warranty into the contract rather than rely only on the general rule, especially where the contract may limit the seller's liability.

For import duties, customs formalities and importing machinery, see Importing machinery for a new factory. Tax and return on investment should be checked by an accountant or auditor.

10. Checklist before deciding to buy a machine or hire

  • Draw the process as it is really done and follow one job from start to finish
  • Collect per-step figures for one to two weeks: usable output, waiting time, WIP, set-up time, rework and downtime
  • Identify the bottleneck and confirm it by temporarily helping that step and seeing deliveries rise
  • Try method, set-up time and scheduling changes at the bottleneck first
  • If you will use overtime or an extra shift, check the latest labour law conditions first
  • Gather every promise sales made: delivery dates, penalties, priority and minimum volumes
  • Compare the promises with real capacity and list customers at risk of late delivery
  • Before buying a machine, review the supplier contract for delivery, acceptance test, warranty, spare parts and the final instalment
  • Have an accountant or auditor check the return and tax calculations
  • Measure again after each change, because the bottleneck may move

Common misunderstandings

  • Myth: Deliveries are slow because we lack machines or people. Correction: Most of the lost capacity is usually at one step, often set-up time, rework or waiting. Measure before buying.
  • Myth: The busiest-looking step is the bottleneck. Correction: The bottleneck is the step whose usable capacity is lowest relative to the volume, not the one where people rush most.
  • Myth: Adding capacity anywhere speeds up delivery. Correction: Adding outside the bottleneck does not help; work just waits in front of it.
  • Myth: Overtime will make the problem go away. Correction: Overtime is bound by labour law, and if you need it every week the bottleneck is not fixed.
  • Myth: What sales promised is a commercial matter unrelated to capacity. Correction: Promised dates and penalties can make the company liable, so compare them with real capacity before accepting work.
  • Myth: The machine supplier guarantees the output anyway. Correction: It depends on what the contract says. Write the acceptance test and warranty clearly before paying the final instalment.

Limits of this guide. It is a general framework. It does not design a specific plant's process or calculate its capacity, which is work for an industrial engineer or production specialist, and it gives no overtime hours or rates, tax or investment-return figures. The answer in a real case can change with the contract wording and the facts.

Further reading

The bottleneck is the one step that decides how much the whole line can deliver, so measure and fix that step before buying machines or hiring, and compare real capacity with what sales promised and what the machine purchase contract says before committing money.

We help companies review what they promised customers in sales contracts, purchase orders and delivery terms, review machinery purchase or outsourcing contracts on delivery dates, acceptance testing, warranty and liability, and prepare an operations improvement plan that fits those contracts. We are not industrial engineers, accountants or tax advisers, and we cannot promise the result of any negotiation with a customer or supplier. Our fees depend on the stage of the matter and the work required. Send us the documents first, and we will confirm the scope of work and the fees in writing before we start. Call +66 92 254 2045 or send us the details. See also business plan and contracts and documents.


This guide is published by Suwanvara Law Firm — a Khon Kaen law firm established in 1986. General information only, not legal advice on a specific matter.

Frequently asked questions

Orders are up but we deliver more slowly. Where do we start?+

Draw the process from order intake to delivery, then collect a few numbers for each step: how much it actually completes per hour or day, how long work waits in the queue, how much work piles up in front of it, set-up time, the share of rework or scrap, and downtime. The step with the biggest pile and the lowest real output is usually the bottleneck.

What is a bottleneck, and why does adding capacity elsewhere not help?+

The bottleneck is the step with the lowest output in the line, so it sets how much the whole line can deliver. Adding a machine or a person at another step only sends more work to wait in front of the bottleneck. Deliveries do not rise, because the line still produces only as much as the bottleneck can.

Can overtime or an extra shift fix it?+

It can be a short-term supplement at the bottleneck step, but it must follow labour protection law: employee consent where the law requires it, the pay the law requires, and no work beyond what the law permits. Check the latest rules with the Ministry of Labour before relying on it, and do not treat it as a permanent substitute for fixing the process.

Which contracts should we review before buying a machine or adding capacity?+

Both sides. On the sales side, check what sales promised on delivery dates, penalties, priority and minimum volumes. On the purchase side, check the supplier contract for delivery and installation dates, the acceptance test, warranty, spare parts and the consequences of late delivery, before committing the investment.

What is our exposure if we deliver late to a customer?+

It depends on the contract and the reason for the delay. Under the Civil and Commercial Code, if a debtor does not perform as the obligation truly requires, the creditor may claim damages (section 215). If the contract fixes a penalty, the creditor may claim it (section 380), and a court may reduce a penalty that is disproportionately high (section 383). Have a lawyer read the contract before you reply to the customer.

Does the same method work for a service business with a backlog?+

Yes, the principle is the same. Map the path of one customer job, for example intake, document check, production, approval, delivery, and measure where work waits longest. Service backlogs often sit at waiting for customer information, waiting for approval, or waiting for one specialist, not at total headcount.