The core answer
Force majeure and a cost increase are different things. Force majeure is an event that could not be prevented despite reasonable care, and it must actually make delivery or performance impossible or late. A cost increase means you can still deliver but at a bigger loss. As a rule that is the risk of the seller or contractor who agreed the price.
When you cannot deliver, do not start from the question "is this force majeure?". Work through four steps in order: (1) what the contract says about force majeure, (2) what the event was and whether it falls within that clause, (3) the real impact on each delivery item (cannot deliver, late, or merely more expensive), and (4) what evidence and alternatives exist. Only then notify the counterparty in writing. This guide does not assume that every problem relieves you of liability. In many cases the answer is "you must still deliver", "you are relieved only in part", or "you need to negotiate".
The law (Civil and Commercial Code, information as of 21 November 2026) Section 8 defines force majeure. Section 205 says a debtor is not in default while non-performance results from circumstances for which the debtor is not responsible. Section 219 releases the debtor when performance becomes impossible through circumstances arising after the obligation was created and for which the debtor is not responsible. Most contracts also have their own force majeure clause, which in practice usually decides the result.
Our practical view Read the clause and collect the evidence before you send a letter. Notify quickly but do not overstate, and offer options alongside the notice so the other side sees you are working on a solution.
Raw-material costs, price-adjustment formulas and accepted purchase orders are covered in a separate guide: Raw-material costs rise during a contract: when can you ask to adjust the price. This guide is about being unable to deliver or perform, not about a higher price.
Who should read which part
| Your situation | What to read |
|---|---|
| Not yet signed | Sections 1 and 2: check which events the proposed clause covers, who must notify, within how many days, and when termination is possible |
| Signed and in use | Sections 3 to 5: assess the event, the impact, the evidence and how to notify before sending the letter |
| Already in dispute | Sections 6 to 8: negotiation options, the consequences of a wrong claim, and the documents to gather; have a lawyer review before you reply |
1. How is force majeure different from a cost increase?
Ask three questions about the event.
- Could it be prevented? Section 8 measures this against the care reasonably expected of a person in that position and situation. A business that trades continuously is expected to hold reasonable reserves or a second source.
- Can you really not deliver? Section 219 requires impossibility. If you can deliver but it costs more or is harder, performance is not impossible.
- Did it arise after the contract and is it outside your responsibility? An event caused by your own fault, or one already known when you signed, may be harder to rely on.
| Event | Impact to check | Usually |
|---|---|---|
| Raw material or labour costs rise but delivery is still possible | Higher cost | Mostly not force majeure. Look at the price-adjustment formula or negotiate |
| Flood or fire at your own plant stops production | Cannot deliver or late | May qualify if genuinely unpreventable and you notify as the contract requires |
| Your only supplier stops because of a serious event and no other source exists | Late or partial delivery | Depends on the clause and the facts; you must show you looked for other sources |
| A government order bans or suspends production, import or transport | Cannot deliver under the order | May qualify if the order did not result from your own breach |
| Freight costs rise or ships and trucks are scarce but a route exists | Higher cost or delay | If you can still deliver, usually not; if the route is fully closed, it may differ |
| Workers strike, or machines break down in the ordinary way | Late | Usually not, because within your control or risk, unless the contract says otherwise |
This table is a general guide, not a ready-made answer. The outcome depends on the contract and the facts of each matter.
The legal consequences also differ. If section 219 applies, the debtor is released from the part that became impossible. For a merely temporary delay, section 205 says that while non-performance results from circumstances the debtor is not responsible for, the debtor is not in default. Neither section removes other duties, such as the duty to notify, to deliver what can still be delivered, and any added duties in the contract.
In a reciprocal contract, section 372 provides as a general rule that if performance becomes impossible for a reason that cannot be blamed on either side, the party who cannot perform has no right to the counter-performance for that part. A seller should therefore not expect to be paid for goods it could not deliver.
2. What should you check in the force majeure clause?
Many business contracts contain one, and it often matters more than the general rules. Check the following.
| Point | What to read carefully |
|---|---|
| Definition and list of events | Is there a list (flood, earthquake, war, government order) or a broad wording, and is there a phrase such as "any other event beyond control"? |
| Excluded events | Are cost increases, currency moves, labour issues, machine breakdowns or supplier fault excluded? |
| Subcontractors and suppliers | Do events affecting them count, and what more must be shown? |
| Duty to notify | Within how many days, to whom, by what channel, with documents attached? |
| Duty to mitigate | Must you look for alternatives, and to what extent? |
| Effect of the clause | Extension of time, temporary suspension, no penalty, or a right to terminate |
| Longest period | After how long may the other side terminate if the event continues? |
| Payments | Are payment duties already due excused? Usually they are not |
| Effect on other rights | Can damages or penalties still be claimed? |
If the contract has no such clause, use the general rules in section 1 and negotiate. If the contract is in English or bilingual, check which version governs; see Thai and English contract versions that conflict.
Before signing, ask for the list of events to match the real business. If you depend on one supplier, negotiate for supplier events to count, or accept that they will not and prepare a back-up source. The effect should also be clear: extension of time and no penalty during the event, not merely a duty to inform.
3. How do you separate the event from its real impact?
When something happens, write three lines before sending anything to anyone. People often blend them until the result is unclear.
- The event What happened, when, where, and who confirms it.
- The impact on you Production capacity, materials, transport or licences affected, and for how many days.
- The effect on the contract with this counterparty Which items cannot be delivered, which are late, which can still be delivered, and which purchase order each belongs to.
Then check three more things.
- Alternatives you could still use Other material sources, another factory, another transport route, partial delivery. If these exist at a cost not out of proportion to the event, the counterparty may argue you can still deliver.
- Your own part Insufficient preparation, late ordering or failing to inform your supplier may mean the event is not treated as unpreventable.
- The time period An event that stops delivery for three weeks does not mean every delay is caused by it. The period after you could produce again must be explained separately.
If the impact is only a higher cost, go to the raw-material cost guide. Do not mix cost into the notice about non-delivery, because it weakens the real event.
4. How should you notify the counterparty when you cannot deliver or perform?
Timing Notify as soon as you know it will have an impact. Do not wait for complete information. If the contract sets a number of days, count from the date the contract specifies (for example the date of the event or the date you became aware) and send before it runs out. A late notice may make the clause unavailable and may give the counterparty grounds to claim added loss.
Form Use the channel the contract requires. If it specifies none, send a letter or an email addressed to a named recipient, dated, and keep proof of sending. If you phone, always follow with a document.
Content The notice should cover:
- the contract and purchase orders concerned;
- the event, its date and who confirms it;
- the impact on each delivery item, listed separately, not "everything is delayed";
- what the company has already done to reduce the impact;
- the expected delivery dates and when you will confirm them again;
- the options you propose, such as partial delivery or another source;
- a request for a reply or a meeting by a stated date;
- attached documents.
Statements to be careful with
| Avoid writing | Why | Write instead |
|---|---|---|
| "The company is fully released from liability under the law" | Overstates what has been checked and invites a challenge | "The company invokes clause X of the contract because of this event" |
| "It was our mistake and we apologise" | May be used as an admission | State the facts and apologise for the inconvenience |
| "Costs rose so we cannot deliver" | Cost is generally not force majeure | Take price to a separate negotiation |
| "We will stop delivering until we agree" | May itself be a breach | Name only the items you truly cannot deliver |
If you are the party receiving the notice (the customer), do not rush to accept that it is force majeure. Ask for information and evidence, check the contract, and reply that you reserve your rights while you review.
5. What evidence should you keep?
The party giving notice must show the event really happened and really had an effect. Collect it before you send the letter.
- The contract, purchase orders, delivery dates and the latest force majeure clause including amendments
- Documents confirming the event, such as a government notice, a weather report, a letter from the supplier, a police report or an incident log
- Dated photographs or video
- Production capacity and stock data before and after the event
- Emails or letters with suppliers and carriers, including refusals
- Records of searching for a substitute source: quotes, dates of contact and why it could not be used
- The affected purchase orders and delivery dates, itemised
- Your notice to the counterparty, proof of sending, and any reply
- Any insurance that may cover the event and the date the insurer was notified, if applicable
Date every document, because dates show whether you notified in time.
6. What negotiation options exist?
Most counterparties want the goods more than they want a dispute. Offering options with evidence usually makes talks easier than quoting the law alone.
| Option | When it fits | What to state clearly |
|---|---|---|
| Partial delivery first | Some items or quantities can be delivered | What is delivered, the date for the rest, payment for what is delivered |
| Postpone the delivery date | Temporary event | The new date and what happens to penalties during the extension |
| Substitute source or factory | The customer can inspect and accept | Specification, manufacturer, who bears the cost difference |
| Temporary specification change | The original material is scarce | The scope of the change and effect on warranty |
| Temporary suspension | The event is continuing | A review date and the conditions for resuming |
| Terminate only part | Delivery is no longer possible | The part terminated, money already paid, materials already made |
Any arrangement that changes the contract should be a document signed by both sides and should say whether penalties or earlier claims are waived, paused or reserved. Silence or continued acceptance of goods should not be used as a substitute for an agreement.
If the negotiation touches price, for example asking the customer to share the cost of a substitute source, treat it as a separate topic and see Raw-material costs rise during a contract.
7. What happens if the counterparty does not accept the force majeure claim?
If the event is ultimately held to fall outside the clause or short of impossibility, non-delivery or late delivery may be a breach. The counterparty may have the following remedies.
- Termination If a party does not perform, the other may set a reasonable period and give notice to perform, and if it is not met within that period may terminate (section 387), or terminate directly under the contract's own clause.
- Damages When a debtor fails to perform properly, the creditor may claim compensation (section 215), generally for loss that would ordinarily result, and including loss from special circumstances if the parties foresaw or should have foreseen them (section 222).
- Penalty or late-delivery charge If the contract provides for one. See Customer deducts penalty or damages from payment.
- Knock-on effect on other contracts If you supply other customers, the delay may pass down the chain. Check those contracts too.
If you receive a letter alleging breach, do not rush to accept or deny it. See Preparing a response to a breach-of-contract allegation.
What improves your position: notifying on time, showing mitigation, offering options and keeping full evidence. What worsens it: silence, late delivery without notice, or invoking force majeure for a problem that is really about cost.
8. Checklist when you cannot deliver or perform
- Read the force majeure clause and the related termination, penalty and liability clauses
- Write three lines: the event, the impact on you, the effect on the contract with this counterparty
- Classify the result: cannot deliver, late, can still deliver, or only a cost increase
- Check whether a workable alternative exists and record your contacts
- Count the contractual notice deadline and send before it expires
- Draft the notice using the headings in section 4, without concluding you are fully released
- Collect evidence as in section 5 and arrange it by date
- Prepare at least two negotiation options with clear dates
- Check the effect on contracts with suppliers, subcontractors, carriers and insurance
- Record any new arrangement in a document signed by both sides
- If you have received a demand or threat to terminate, have a lawyer review before you reply
9. Hypothetical example: a packaging plant cannot deliver because of a flood at its supplier
This example is not a real case. The figures are illustrative only.
Company A makes plastic boxes for customer B under a framework contract. An open purchase order covers 40,000 pieces due on the 10th of the month. The contract's force majeure clause lists "flood, fire, natural disaster and government order", extends delivery time for as long as the event lasts, requires written notice within 7 days of becoming aware of the event, and says nothing clear about events affecting suppliers, neither excluding nor including them.
On the 3rd a flood hits the plant of the resin supplier, A's only supplier, which stops production for about 3 weeks. At the same time, resin from other sources costs about 25% more than before.
A checks in order.
- Event and clause Flood is on the list, but it happened at the supplier, not at A's plant. The contract is silent on this type of event. A is careful not to write that it is released, and asks B to confirm that this event counts.
- Real impact On this order A has enough resin stock for 12,000 pieces. The other 28,000 cannot be made while the supplier is down. So the "cannot deliver" part is the 28,000 pieces, not the whole order.
- Alternatives A contacts two other suppliers and finds they can deliver in week two, at a price 25% higher. So delivery is not impossible. The price difference is a cost matter. A takes it to a separate negotiation and does not write in the notice that "costs rose so we cannot deliver".
- Notice On the 5th, within the 7 days, A sends B a letter with photos of the flood, the supplier's letter and emails to other producers. It offers three options: deliver 12,000 pieces on time, deliver the rest in week three when material arrives, or use resin from another source if B accepts the specification.
- Possible result B accepts the first part and agrees to defer the rest in a memorandum signed by both sides, which suspends penalties during the extension and reserves the price difference for further negotiation. If B refuses, A must still be ready for the risk of late-delivery penalties and termination of the part it could not deliver in time.
The example shows that one event can have a part that may fall within the clause and a part that is purely a cost matter. Separate the two from the moment of the notice.
Common misunderstandings
- "A big cost increase is force majeure" Not as a rule. Force majeure must be unpreventable, and section 219 requires impossibility. A cost that rises while delivery remains possible does not qualify. Look at the price-adjustment formula and negotiation.
- "The contract has a force majeure clause, so I need to do nothing more" Clauses usually set conditions, such as notice within a number of days and efforts to mitigate. If you do not meet them, you may not be able to rely on the clause.
- "It happened at my supplier, so it is my force majeure" Not always. Check whether the contract counts supplier events, whether the event was genuinely unpreventable, and whether other sources existed.
- "Force majeure releases me from everything at once" No. Section 219 releases only the part that became impossible. Temporary delay is addressed by section 205, and duties to notify, to deliver what can still be delivered, and payments already due may remain.
- "I sent a notice, so the counterparty has to accept it" A notice is not a request for consent and does not bind the other side. They may challenge it, so keep evidence and options ready.
- "It was force majeure last time, so it is this time" Assess it afresh each time. An event known or foreseeable at signing, or one you could have prepared for but did not, may be harder to rely on.
Further reading
- Raw-material costs rise during a contract: when can you ask to adjust the price
- Customer deducts penalty or damages from payment
- Preparing a response to a breach-of-contract allegation
- Monthly service contracts: MSA and SLA
- Liability and indemnity in contracts
- Contract review for companies without a legal department
Force majeure is an unpreventable event that genuinely stops delivery, not something that has become more expensive. Check the clause, the event, the real impact and the evidence, then notify the counterparty in writing with options for negotiation, without assuming every problem relieves you of liability.
We review force majeure clauses and related terms, assess whether the event falls within them, draft notices to and replies from counterparties, assemble the evidence file, and prepare negotiation proposals or a written amendment to the contract. We are not tax advisers or accountants, we are not an insurer, and we cannot promise that an event will be treated as force majeure or what the outcome of a negotiation with the counterparty will be. Fees depend on the stage of the matter and the work required. Send us the documents first, and we will give you the scope of work and fees in writing before we start. Call +66 92 254 2045 or send us the details. See also contracts and documents and alternative dispute resolution.