Skip to main content
SUWANVARA LAWFIRM
Suwanvara Law Firm Co., Ltd.
SUWANVARA LAWFIRM
SUWANVARA LAWFIRM
Suwanvara Law Firm Co., Ltd.
Business Law

Setting Up a Factory in Thailand: What Has to Happen First, and What Has to Wait

The order of steps from company formation to first production — investment promotion, site, zoning, building, factory licence, machinery, utilities and people — and the sequencing mistakes that cost foreign manufacturers months.

Suwanvara Law FirmIndustrial & Investment TeamSeptember 13, 202611 min read

Why the order matters more than the paperwork

Foreign manufacturers setting up in Thailand rarely fail on a single permit. They lose time because steps were done in the wrong order: machinery shipped before the promotion certificate, land signed before zoning was checked, a building finished before anyone confirmed which factory class it would house.

Each of those is a reasonable business decision made under deadline pressure. Each turns an administrative step into a correction. This guide sets out the sequence, with the dependencies between steps, so the decisions that cannot be undone are made first.

1. Decide what the Thai entity will actually do

Start with activities, not with the company.

  • Manufacturing is generally open to foreign-majority companies.
  • Selling domestically through your own sales operation, installation, maintenance and after-sales services may be restricted activities for a foreign-majority company.
  • Owning land is restricted for foreign companies unless a specific route permits it.

Write down everything the Thai company will do in its first three years, including the services customers will expect. That list decides whether you need investment promotion, a foreign business licence, a Thai-majority structure, or none of these. See whether your Thai company needs a foreign business licence.

2. Choose the route: promotion, estate, both or neither

Two decisions shape everything after them.

Investment promotion. A promotion certificate can lift foreign-ownership restrictions for the promoted activity, permit land holding for the project, give import duty exemption on machinery, and ease work permits for foreign experts. It also comes with conditions, reporting and deadlines. See living with promotion after approval.

Industrial estate. An estate gives a single authority for many approvals, infrastructure that already exists, and a land route for foreign companies. Outside an estate, zoning, access, utilities and land holding need to be worked out parcel by parcel. See factory and industrial-estate law and what changes when your site is outside an estate.

3. Form the company to match the route

Only now form the operating company, with objectives, capital and shareholding that fit the route chosen. A company formed first and adjusted later works, but every adjustment is a registration, and a promotion application measured against the wrong company particulars is slower.

If there are several foreign founders, settle the shareholding decisions before registration. See shareholding decisions in a promoted company.

4. Secure the site: buy, lease, or lease ready-built

OptionSuitsWhat to check first
Buy land and buildLong-term, large or specialised plantsLand-holding route, zoning, access, utilities, title
Lease land and buildEstate or private sites where purchase is not permitted or not wantedLease term, registration, what happens to the building at the end
Lease a ready-built factoryFaster start, smaller plants, uncertain volumesApproved use, power, the landlord's documents, fit-out limits

Before signing anything, do land and title diligence. See land due diligence for a project site and leasing a ready-built factory.

5. Confirm zoning and the factory class before design

Two facts should be fixed before an architect finishes drawings.

Zoning. The town plan decides whether the parcel may host this type of factory at all.

Factory class. Under the Factory Act as amended in 2019, a plant counts as a factory where its machinery reaches 50 horsepower or it employs 50 workers or more. Factories are then divided into classes, and the class decides whether you simply operate, notify, or must hold a licence before operating. The class depends on the process and the scale, so it comes from the machinery list and headcount plan. See your factory licence in Thailand.

At the same stage, screen whether the project type and size require an environmental impact assessment. Where one is needed, it runs before other approvals can complete and is often the longest item in the whole schedule.

6. Building approvals and the construction contract

Obtain the building permit for the approved use, and sign a construction contract that deals with delay, variations, defects and termination. See contract terms an owner needs before construction starts.

Changes during construction that alter the process layout or capacity are worth checking against the factory licensing position before they are built, not after.

7. Machinery: order after the import route is secured

Where the project relies on duty exemption under investment promotion, machinery should be imported under that route, within its time limits, and matching the approved list. Machinery that arrives before the route is in place generally cannot be brought back into the exemption. Used machinery has its own criteria. See importing machinery for a new factory.

8. Utilities: apply early

Power capacity is the utility that most often delays a start. Large connections and transformer work take time and are sequenced by the utility, not by your production plan. Apply as soon as the site and load are known. Water supply, wastewater treatment and discharge conditions follow the same principle.

9. The factory licence or notification

With the building complete and machinery installed, the licensing or notification step for your class can be completed. For licensed classes, operation starts only once the licence is granted. Licences under the amended Act no longer carry a fixed renewal cycle, but they do attach to the operator, the site and the approved process, so later changes need amendments.

10. People

  • Foreign managers and technicians need work permits before they start work, including installation specialists.
  • Thai staff need contracts, social security registration and, from ten employees, work rules. See HR for a small foreign-owned factory.
  • Customer audits may impose standards beyond Thai law. See RBA requirements for suppliers.

11. Before the first shipment

Check product standards that apply before goods can be sold, customs registrations for import and export, and tax registrations. See mandatory product standards.

The sequencing mistakes we see most

  1. Machinery shipped before the promotion certificate, losing duty exemption
  2. Land signed before zoning and the land-holding route were confirmed
  3. Building designed before the factory class was known
  4. Power applied for after construction, delaying start-up
  5. Foreign installation engineers arriving without work permits
  6. Process or capacity changed after licensing without an amendment
  7. Domestic sales and services started under a structure that only permits manufacturing

What to bring to a first meeting

  • The products, processes and planned capacity
  • A draft machinery list with power ratings and origin, new or used
  • Headcount plan, including foreign staff
  • Candidate sites or estates, and whether you intend to buy or lease
  • Whether investment promotion has been discussed or applied for
  • How products will be sold: export only, or domestic as well

With those, the sequence and its dependencies can be mapped for your project specifically.

Frequently asked questions

Does a foreign company need a Thai partner to manufacture in Thailand?+

Usually not for manufacturing itself. Most manufacturing activities are not among the businesses restricted for foreign-majority companies. The questions arise at the edges: selling domestically through your own distribution, installation or after-sales services, and owning land. Investment promotion or an industrial estate route can address several of these, which is why the route decision comes before the company is formed.

Should we apply for investment promotion before or after forming the company?+

Decide the route before you commit spending. An application can often begin before the operating company exists, with the company formed afterwards, and the certificate then shapes what the company may do, where it may be located and which machinery it may import free of duty. The costly mistake is ordering machinery or signing a site before the promotion position is known.

Can we start trial production while the factory licence is pending?+

Not where the plant falls into the class that requires a licence before operation. A plant below the licensing threshold, or in the class that only notifies, is treated differently. Confirm the factory class from the planned machinery and headcount before construction, because that single fact sets the licensing timeline.

Is it better to build in an industrial estate or on private land?+

Estates bring a single authority, ready infrastructure and a route to land holding for foreign companies, at the cost of estate rules and fees. Private land can be cheaper and closer to suppliers, but zoning, access, utilities and the land-holding structure all become your problem. Many foreign manufacturers start by leasing a ready-built factory in an estate and decide later.

What is the most common sequencing mistake?+

Treating licences as paperwork that follows the physical work. Machinery imported before a promotion certificate loses the duty exemption; a building constructed before the factory class is confirmed may need redesign; a process changed after licensing needs an amendment. Each is a small decision at the time and a large correction later.

How long does the whole process take?+

It depends on the route, the site, the factory class and whether an environmental assessment is required, so any single figure would mislead. What we can give once we know those facts is a sequence with the dependencies marked, showing which steps can run in parallel and which cannot start until another finishes.